Find out more about how the IRS team helped Walsall County Council, at their Civic Data Centre, install control systems which were designed bespoke to their requirements below.

Project Overview

Walsall County Council required the IRS team to design, supply, and install three replacement close control systems within the main council data centre, using a range of carefully selected equipment. Implementation of the project was crucial - due to the critical nature of the data room. No more than one system could be off at any one time; meaning efficient planning and implementation had to be applied. We were required to made control adjustments to ensure the existing fire alarm cut outs were operational also. We were pleased to have completed the project by August 2019.

Equipment Used

We opted for the Denco DXF Range, paired with remote Mitsubishi Electric Condensers. The advantages of this type of system for the application were lighted indoor units, quieter systems, less maintenance (required within high confidential areas as compressor and main fridge circuit components outside), and less refrigerant; meaning an overall reduction in co2 output. 

We have a wide range of certifications and accreditations, which we always strive to make use of in our projects. In this case, we made great use of our Mitsubishi Electric Business Solutions Partner accreditation, which you can find out more about here.